Posted by Grant Foraker on July 25, 2005 at 12:44:21: Uploaded files: 1
In Reply to: Re: Comet Project Manager question posted by Brian Levantine on July 25, 2005 at 11:10:23:
CPM, see screenshot.
The first project I opened today was on the NNC directory. That's closed and I now have a project from the PAL directory open. The Add Files keep defaulting to NNC even if I stop and restart UE.
I built the PRJ file using my own program, NEWPRJ, based on what I'd seen in the PRJ's created by CPM. Is there a record in the PRJ that contols this that I might have missed?